Project Update

Small sample of Project Update information from another project.

August 5, 2016

Water Improvements:
Week of 07/28/2016:

  • All water main system improvements were completed this week. The new water system is now active throughout the project limits.
  • Preparation for final landscaping and sidewalk/curb installation was ongoing.
  • Asphalt patching work was started.

Week of 08/04/2016:

  • Preparation for final restoration work will continue and sidewalk and curb placement will be completed.

We greatly appreciate your patience during construction.